ICRA Nepal assigns long-term rating of [ICRANP] LBB to the long-term loans, and short-term rating of [ICRANP] A4+ to the short-term loans of Makari Gad Hydropower
Wed, Sep 18, 2019 12:00 PM on Credit Rating, Latest,
ICRA Nepal has assigned a long-term rating of [ICRANP] LBB (pronounced ICRA NP L double B) to the long-term loans, and a short-term rating of [ICRANP] A4+ (pronounced ICRA NP A four plus) to the short-term loans of Makari Gad Hydropower Private Limited (MGHPL).
Credit strengths
- Experienced institutional promoters from power sector
- Healthy dry energy mix and higher contract PLF to support return and debt coverage indicators
- Minimal funding gap with injection of 82% promoter equity so far and fully tied-up debt component
- Low tariff risk, given presence of long-term PPA at predetermined tariff rates and escalations
- Low offtake risk on the back of PPA and demand-supply gap; however, conditional offtake clause for 10% of energy
Credit challenges
- High project execution risk amid tight construction timeline; only ~15% of project work completed so far
- Risk of tariff escalation loss and late COD penalty
- Hydrology risks remain high, given lack of deemed generation clause in PPA
- Foreign exchange fluctuation risk
About the company
Makari Gad Hydropower Private Limited (MGHPL), incorporated on February 4, 2014 as a private limited company by two institutional promoters viz. Hydro Vision Company Private Limited (Nepal) and Sky Power Renewable, LLC (LLC No. 11164/2013 in Cook Island). Later, the company majority share has been acquired by LTL Energy Private Limited, a Sri Lanka. LTL Energy is a 100% subsidiary of LTL Holdings Private Limited, Sri Lanka. LTL Energy received FDI approval on September 16, 2018 for a total sum of NPR ~803 million, which is 97.5% of the total issued share capital of ~NPR 824 million.
MGHPL is developing the 10-MW Makari Gad Hydroelectric Project in the Darchula district of Sudurpashchim of Nepal. The estimated development cost of the project is NPR 2,050 million (~NPR 205 million per MW) in a debt equity ratio of 70:30. The debt is yet to be disbursed as the consortium is waiting for the rating. The debt portion is being financed by a consortium of three Class “A” banks led by Sanima Bank Limited that has been rated [ICRA NP IR] A-. The main promoter has already injected ~82% of the total equity requirement for the project while the rest will be injected soon. The project construction commenced in November 2018 and was ~15% complete as of mid-July 2019.
Source: ICRA Nepal